Performance audit
Department of Administration, State Public Works Division, Project Identification, Cost Estimation, and Reporting
Legislative Auditor report LA26-01, issued January 16, 2025, contains five recommendations on project identification, cost estimation, and reporting at the State Public Works Division. The division accepted all five. As of April 15, 2026, the Legislative Auditor assessed 4 as fully implemented and 1 as partially implemented.
- Recommendations
- 5
- Issued
- January 16, 2025
- Agency response
- The State Public Works Division accepted the five recommendations.
- April 15, 2026 status
- 4 fully, 1 partial, 0 no action
What the report says
Purpose. Determine whether the division had adequate controls to identify, complete, and report on construction projects.
Scope. Activities from July 1, 2020, through June 30, 2023, including Capital Improvement Program projects approved in 2019.
- Testing of 13 closed projects in a sample of 20 projects from the 2019 Capital Improvement Program identified over $18 million in savings that the division did not present to the Interim Finance Committee for transfer to other approved projects.
- The biennial report to the Legislature on recommended maintenance included costs for 732 projects already completed, an error of about $51 million. Using outdated costs, the auditors predict this understated the cost of recommended maintenance in 2023 by as much as $220 million.
- Four of five Capital Improvement Program projects tested had no evidence that project managers coordinated with the facility-condition-assessment team or used those reports when developing projects.
- The report says a comparison of estimated costs in the Capital Improvement Program with actual project costs showed an effective estimating process, and that the division often did not retain documents supporting the estimates.
- In 2023 the division oversaw about 2,400 state facilities comprising 10.1 million square feet. Administrative expenditures for fiscal year 2023 were about $7.5 million, and the division also received almost $400,000 in General Fund appropriations that year. As of May 2024, 120 of 146 authorized positions were filled, an 18 percent vacancy rate.